PM Test Center

FREE daily project management test questions for PMP®, CAPM®, and Project+ exams!

PM Test Center

CPI and SPI: The under-rated indicators

Six months into a year long project your CPI is 0.8. However, your SPI is 1.2. This means that the project is:

A. Ahead of schedule and under budget
B. Ahead of schedule and over budget
C. Behind schedule and under budget
D. Behind schedule and over budget

Answer: B. Ahead of schedule and over budget
For both Cost Performance Index (CPI) and Schedule Performance Index (SPI), 1.0 is exactly as planned, over 1.0 is good and under 1.0 is bad. So in this case, the CPI is bad and SPI is good. In this example, the CPI means you are getting $0.80 of value out of every $1 spent (see CPI -- what is it trying to tell me?) while the SPI means you are progressing at 120% (i.e. 20% better than planned) of the baseline.

0 comments:

Post a Comment

About Gabe Young