WBS breakdown

While working on a WBS, breaking down work into manageable parts is known as:

A. Decomposition
B. WBS dictionary
C. Work package
D. Scope management

Answer: A. Decomposition
Work packages are the lowest level of a WBS. The process of getting to that point is called decomposition.