You are working on a project to build a small bridge near the town entrance and decide to gather risks using the Delphi technique. You know that once you have identified all the risks at this stage, you will have your initial:
A. Monte Carlo Simulation
B. Risk register
C. Performance report
D. Risk management plan
Answer: B. Risk register
The risk register is the primary output from the Identify Risks process; the Delphi technique is one of the tools and techniques that may be used. Subsequent risk processes include the risk register as their inputs as well as providing risk register updates as their outputs.