One of your monthly reports claim that your project has a SV of -1000. How would you describe it to your sponsor?
A. The project is behind schedule
B. The project is ahead of schedule
C. Impossible to have a negative SV
D. Not enough information
Answer: A. The project is behind schedule
SV (schedule variance) is simply a measure of how the project is performing in terms of schedule. A positive number is good, ahead of schedule, while a negative number is bad, behind schedule. SV is derived from EV (earned value) minus PV (planned value).
PM Test Center
- Perform Integrated Change Control process - 4/20/2015 - Gabe Young
- Gantt chart weakness - 4/19/2015 - Gabe Young
- Scope management plan - 4/18/2015 - Gabe Young
- Work package size - 4/17/2015 - Gabe Young
- Management skills - 4/16/2015 - Gabe Young
Subscribe to:
Post Comments (Atom)
0 comments:
Post a Comment