You released an RFP but several of the prospective suppliers have questions regarding some of the scope. You determine that the best way to listen to their concerns and convey your message is to have a(n):
A. Invitation for bid
B. Qualified supplier list
C. Bidder's conference
D. Independent estimate
Answer: C. Bidder's conference
A bidder's conference is a meeting with suppliers to ensure they have a good understanding of the procurement document.
PMP® and CAPM® Exam Alert
The current PMP® and CAPM® exams reflect the lastest version of the PMBOK® Guide. Any exam taken on or after June 30, 2009 is based on the PMBOK® Fourth Edition.
Email Subscription
Labels
- closing (3)
- communications (2)
- cost (7)
- executing (7)
- framework (2)
- human resources (3)
- initiating (4)
- integration (4)
- monitoring and controlling (8)
- planning (13)
- pmtestcenter.com (1)
- procurement (3)
- professional responsibility (2)
- project selection (1)
- quality (4)
- risk (4)
- scope (1)
- time (4)
0 comments:
Post a Comment