What is the name of the document that formally authorizes a project?
A. Project management plan
B. Requirements documentation
C. Project charter
D. Project scope statement
Answer: C. Project charter
According to the PMBOK®, Develop Project Charter is the process of developing a document that formally authorizes a project or a phase and documenting initial requirements that satisfy the stakeholders' needs and expectations.