You are performing a quality audit to determine whether or not your project team's testing activities follow your organization's project policies. What process are you working in?
A. Perform Quality Assurance
B. Perform Quality Audit
C. Perform Quality Control
D. Perform Quality Activities
Answer: A. Perform Quality Assurance
The key word in the question is audit. Auditing is a primary tool in the quality assurance. Essentially, you are auditing to ensure appropriate quality standards. There is no such process as Perform Quality Audit or Perform Quality Activities.