You, the project manager, have a deliverable due in three days, just in time for your client to showcase at her annual event. However, you just learned that a shipment has been delayed and it will push your delivery date out by a day. What is the first thing you should do?
A. Notify your client
B. Notify your manager
C. Evaluate the options
D. Assess the impact
Answer: D. Assess the impact
Any time you are in a scenario like this, the first two things you should do before notifying your manager or your client are to (1) assess the impact and (2) evaluate the options. In other words, take a look at what happened and figure out some alternatives. So by the time you have to communicate to your manager/client, you already have a story and recommendation ready to go.
PMP® and CAPM® Exam Alert
The current PMP® and CAPM® exams reflect the lastest version of the PMBOK® Guide. Any exam taken on or after June 30, 2009 is based on the PMBOK® Fourth Edition.
Email Subscription
Labels
- closing (3)
- communications (2)
- cost (7)
- executing (7)
- framework (2)
- human resources (3)
- initiating (4)
- integration (4)
- monitoring and controlling (8)
- planning (13)
- pmtestcenter.com (1)
- procurement (3)
- professional responsibility (2)
- project selection (1)
- quality (4)
- risk (4)
- scope (1)
- time (4)
Blog Archive
-
▼
2009
(35)
-
▼
July
(27)
- Stages of team development
- Formal project authorization
- Quality audit
- Project -- what's the official definition anyway?
- Defect frequency
- Risk response strategy
- Test the deliverable
- False information on the PMP® application
- Situational heuristic
- Labor cost
- Contract communications
- If we keep doing it, we'll get better, right?
- WBS breakdown
- Lag or lead? Critical path or non-critical path?
- Contract types 101
- Opportunity cost
- Customary gifts
- Maslow Hierarchy of Needs
- One sigma, two sigma, three sigma, six sigma!
- PERTy formula
- Critical path, show us the way
- Why am I creating a risk management plan again?
- Win-win conflict resolutions
- CPI and SPI: The under-rated indicators
- CPI -- what is it trying to tell me?
- Continuous improvement
- Organization types
-
▼
July
(27)
0 comments:
Post a Comment