Which of the following organization types does the project manager have the most power?
A. Functional
B. Weak matrix
C. Strong matrix
D. Projectized
Answer: D. Projectized
Projectized organizations grants project managers with total control of their projects. That means team members report directly to the project manager. Functional organizations, conversely, provides project managers with the least amount of power since the team members report to a functional, or line of business, manager.
PMP® and CAPM® Exam Alert
The current PMP® and CAPM® exams reflect the lastest version of the PMBOK® Guide. Any exam taken on or after June 30, 2009 is based on the PMBOK® Fourth Edition.
Email Subscription
Labels
- closing (3)
- communications (2)
- cost (7)
- executing (7)
- framework (2)
- human resources (3)
- initiating (4)
- integration (4)
- monitoring and controlling (8)
- planning (13)
- pmtestcenter.com (1)
- procurement (3)
- professional responsibility (2)
- project selection (1)
- quality (4)
- risk (4)
- scope (1)
- time (4)
Blog Archive
-
▼
2009
(35)
-
▼
July
(27)
- Stages of team development
- Formal project authorization
- Quality audit
- Project -- what's the official definition anyway?
- Defect frequency
- Risk response strategy
- Test the deliverable
- False information on the PMP® application
- Situational heuristic
- Labor cost
- Contract communications
- If we keep doing it, we'll get better, right?
- WBS breakdown
- Lag or lead? Critical path or non-critical path?
- Contract types 101
- Opportunity cost
- Customary gifts
- Maslow Hierarchy of Needs
- One sigma, two sigma, three sigma, six sigma!
- PERTy formula
- Critical path, show us the way
- Why am I creating a risk management plan again?
- Win-win conflict resolutions
- CPI and SPI: The under-rated indicators
- CPI -- what is it trying to tell me?
- Continuous improvement
- Organization types
-
▼
July
(27)
0 comments:
Post a Comment