The PERT formula is typically calculated as:
A. (O+M+P)/6
B. (O+4M+P)/6
C. (O+M+P)/3
D. (O+4M+P)/3
Answer: B. (O+4M+P)/6
PERT is a weighted average, typically with emphasis on the most likely (M). So if you're going to calculate 1x optimistic plus 4x most likely plus 1x pessimistic, that's six variables. Therefore, you would divide by six to get a weighted estimate.
PMP® and CAPM® Exam Alert
The current PMP® and CAPM® exams reflect the lastest version of the PMBOK® Guide. Any exam taken on or after June 30, 2009 is based on the PMBOK® Fourth Edition.
Email Subscription
Labels
- closing (3)
- communications (2)
- cost (7)
- executing (7)
- framework (2)
- human resources (3)
- initiating (4)
- integration (4)
- monitoring and controlling (8)
- planning (13)
- pmtestcenter.com (1)
- procurement (3)
- professional responsibility (2)
- project selection (1)
- quality (4)
- risk (4)
- scope (1)
- time (4)
Blog Archive
-
▼
2009
(35)
-
▼
July
(27)
- Stages of team development
- Formal project authorization
- Quality audit
- Project -- what's the official definition anyway?
- Defect frequency
- Risk response strategy
- Test the deliverable
- False information on the PMP® application
- Situational heuristic
- Labor cost
- Contract communications
- If we keep doing it, we'll get better, right?
- WBS breakdown
- Lag or lead? Critical path or non-critical path?
- Contract types 101
- Opportunity cost
- Customary gifts
- Maslow Hierarchy of Needs
- One sigma, two sigma, three sigma, six sigma!
- PERTy formula
- Critical path, show us the way
- Why am I creating a risk management plan again?
- Win-win conflict resolutions
- CPI and SPI: The under-rated indicators
- CPI -- what is it trying to tell me?
- Continuous improvement
- Organization types
-
▼
July
(27)
0 comments:
Post a Comment